Pick a deadline and see, week by week until then, the work due, its points, and the questions your team still has to answer.
On this page
Overview#
Weekly Look-ahead answers what is coming due between now and the deadline, and which questions do we need answered on the way? Pick a deadline, narrow the work with the usual filters, and the report lists every week from this one to the deadline's week. Each week shows the work due in it and the questions placed in it, so a week that is heavy with open questions stands out before you reach it.
Open Measure Performance and pick Weekly Look-ahead under Agile, or press Cmd-K / Ctrl-K and type Report: Weekly Look-ahead. It uses the same permission as the Current Progress report, so anyone who can see Current Progress can see it.
Choosing the deadline and the scope#
Pick a date in Deadline in the toolbar. It starts eight weeks from today, and your browser remembers the last one you chose. The deadline must be today or later and no more than 104 weeks (about two years) away; otherwise the report tells you to pick another date.
For and Filters narrow the work as on other reports, so you can look ahead for one workstream, one board, or any saved filter. There is no Range, no Summarize by and no chart options: the report is a list, and today and the deadline set its span.
Reading the report#
Weeks run Monday to Sunday, in your own time zone. Each week has a header with its dates, how many items are due and their total points, and how many of its questions are still open. A week with three or more open questions has its count shown in red.
Under the header:
- Work due that week — every item whose due date falls in the week, with its Status, Assignee, Due date and Points, earliest due first.
- Questions — each question placed in the week, marked Question while open or Answered once it is, with a short excerpt, why it sits in that week, who asked it (the customer for a question a requester asked on a ticket), the article it was asked on if any, and the work it belongs to.
A week with nothing in it says Nothing due and no questions this week.
Three more lists appear only when they have something in them:
- Overdue — unfinished work due before today, and open questions whose week has already passed.
- Open questions with no date — open questions with no need-by date on work that has no dates yet.
- Open questions on finished work — open questions whose work is all finished. They are listed only here, so they never make a week look heavy, but they are still waiting for an answer.
How a question gets its week#
A question is placed by the first of these that applies:
- Answered — the week it was answered (Answered and the date).
- Need-by date — the week of the date it is needed by (Needed by and the date).
- Planned work — the week its work is first planned: the earliest start date, or else due date, of the work it belongs to (Work planned from and the date).
- Otherwise it has no date and is listed under Open questions with no date.
A question asked on a Knowledge Base article belongs to the work items the article is linked to, so it is included when that work is in scope.
Example. You set the deadline to the end of next quarter for the Checkout redesign workstream. The week of March 9 shows 6 items and 21 points, and 4 open questions in red: two need answers by March 11 and two sit on work that starts that week. Ask for those answers now, before the week arrives, and check Open questions on finished work for anything the team closed without answering.
Pitfalls#
- Only work with a due date is listed in a week. Work with no due date never appears in a week, though its questions can, through its start date.
- Very large scopes are trimmed. When more work or questions match than the report reads, it says so at the top. Narrow the filters to see everything.
- There is no export. The report is a list on screen only.